Project Timeline

In Home Consultation
Photo/Measure

Design Phase

2-4 Weeks

Design Presentation

Final Selections Phase

2-4 Weeks

Contact

Stage Projects in our Warehouse:
Order All Materials/Products
Pull Permits

20-24 Weeks

Start Date

Construction

See Below

Finish Date

Construction Phase

  • Kitchen 4-10 Weeks
  • Bathroom 4-8 Weeks
  • Laundry / Mudroom 2-6 Weeks
  • Basement / Bar / Pubroom 4-6 Weeks
  • Whole House Projects 3-4 Months

Average Costs

Kitchen
$60,000 to $150,000+
Master Bath
$50,000 to $80,000+
Hall Bath
$35,000 to $50,000+
Laundry/Mudroom
$20,000 to $30,000+
Bar
$20,000 to $40,000+
Basement
$75,000 to $200,000+
Room Addition
$150,000 to $500,000+

Let's Talk

Schedule a Free In-home Kitchen Remodel Consultation with Our Award-winning Kitchen Designers.

Get Started Learn More
Kitchen Kraft Inc.
Kitchen Kraft Inc.
7079 Huntley Rd.Columbus OH, 43229
(614) 449-7200
Monday – Friday
9AM – 5PM
(by appointment only)
Rated 4.6 out of 5 based on 85 reviews
©2023 Kitchen Kraft Inc. All Rights Reserved.